Milestones

  • 4 April 2006 Letter of intent signed by DELTA and EDF
  • 26 April 2006 The Council of State declares all appeals against the construction of the Sloe Centrale Plant null and void, making the environment permit irrevocable.
  • 28 April 2006 Tender issued to construction companies; start of the tendering process for building the Sloe Power Plant.
  • 18 July 2006 DELTA and EDF sign the joint development agreement.
  • 15 September 2006 Offers received from construction companies.
  • 22 December 2006 Siemens chosen as the principal constractor; Siemens willl deliver the power plant as a turnkey project.

  

  • 15 March 2007 The construction contract and the Long-Term Service Agreement with Siemens are final. By signing the
    Notice to Proceed the project is now definite, with a guaranteed investment of almost 600 millions euros.
  • 29 March 2007 Sloe Centrale B.V. founded by the shareholders EDF (50%) and DELTA (50%).
  • 28 June 2007 Groundbreaking ceremony for the construction of the Sloe Power Plant; 1st pile see Photo impression

     

  • 28 March 2008 Financial close for the construction of the Sloe Power Plant
  • 24 June 2008 Generator 1 on site see Photo impression
  • 4 August 2008 Gas turbine 1 on site.
  • 4 September 2008 Generator 2 on site
  • 16 September 2008 Gas turbine 2 on site

 

  • 18 February 2009 Topping out of the Sloe Power Plant See Photo impression
  • 9 June 2009 First firing of gas turbine 1
  • 30 June 2009 First synchronisation; production of electricity from Unit 1
  • 12 July 2009 First firing of gas turbine 2
  • 21 July 2009 First synchronisation; production of electricity from Unit 2
  • 20 October 2009 Provisional takeover of Unit 1
  • 13 December 2009 Provisional takeover of Unit 2
  • 12 February 2010 Official inauguration of the Sloe Power Plant see Photo impression